Hanoi 2nd metro route elevated tracks to be tested
![A train of the Nhon–Hanoi Railway Station metro line. Photo by VnExpress/Giang Huy.](images/2021/07/01/chaythujpeg32431625050323-1625-2789-5931-1625110555-680x408.jpg)
Trains will run 8.5 kilometers from Nhon in Bac Tu Liem District to the University of Transport and Communications in Dong Da District.
Operators and foreign experts will test the systems on six of the 10 trains that have arrived so far.
The elevated section is now 90 percent complete while the line, which will also run four kilometers underground, is 70 percent finished.
In all it will run 12.5 kilometers through the districts of Bac Tu Liem, Nam Tu Liem, Cau Giay, Ba Dinh, Dong Da, and Hoan Kiem.
Continuous reading
HCMC considers new metro lines, more connectivity
![HCMC considers new metro lines, more connectivity](images/2023/07/24/image-1690185949.jpg)
Traffic news - 24/07/2023
HCMC considers new metro lines, more connectivity
NA members call for changing law to add birthplace to passports
![NA members call for changing law to add birthplace to passports](images/2022/10/27/image-1666839369.jpg)
Traffic news - 27/10/2022
NA members call for changing law to add birthplace to passports
Vietnam's biggest airport in the making still stuck at site clearance
![Vietnam's biggest airport in the making still stuck at site clearance](images/2022/10/17/image-1665971784.jpg)
Traffic news - 17/10/2022
Vietnam's biggest airport in the making still stuck at site clearance
Hanoi considers 6th metro line linking airport to new urban area
![Hanoi considers 6th metro line linking airport to new urban area](images/2022/10/14/image-1665732548.jpg)
Traffic news - 14/10/2022
Hanoi considers 6th metro line linking airport to new urban area
6,600 families to be relocated to extend North-South expressway
![6,600 families to be relocated to extend North-South expressway](images/2022/10/14/image-1665732535.jpg)
Traffic news - 14/10/2022
6,600 families to be relocated to extend North-South expressway