Prolonged delay sees HCMC metro operator run out of funds

02:55 11/03/2022 - Traffic news
Ho Chi Minh City should ask for supplementary funding from the central government to support the operator of its first metro line, the Ministry of Planning and Investment said.
Prolonged delay sees HCMC metro operator run out of funds
Prolonged delay sees HCMC metro operator run out of funds

 

A wholly state-owned firm, HCMC Urban Railway Company No. 1 (HURC1), the operator of HCMC’s metro line No. 1, has run out of funds, the city confirmed in February.

HURC1 came into life in 2015 based on the initial plan for the metro line to be up and running within 2018. At the time of its establishment, the company was granted charter capital of VND14 billion ($$613,000) to purchase office equipment and no operating budget.

According to the company's establishment plan and agreement between the Vietnamese government and Japan International Cooperation Agency, which funds the project, before the line is operational, HURC1 would have no revenue, and therefore the city must allocate budget to ensure its operation. Once the line operates, HURC1 would start earning revenue.

However, as construction fell far behind schedule, the company ran out of funds.

HCMC’s metro line No. 1 costs over VND43.7 trillion ($1.89 billion) and spans around 20 kilometers, stretching from Ben Thanh Station in District 1 to Long Binh Depot in Thu Duc City.

After several delays, the project was set to be completed at the end of 2021 and enter commercial operations this year but was delayed again due to pandemic impacts.

It is now nearly 90 percent complete and expected to start operation in 2023.

According to the Ministry of Planning and Investment, HCMC cannot raise the firm's charter capital as the metro line has yet to operate and therefore, it has told the city administration to ask for state budget to support the firm.

The lack of funds has put HURC1 in many difficulties, including in organizing courses to train drivers for the line.

Once the line starts operation, the company would need around 700 staff compared to just around 15 at present.

Read More in This Category

HCMC considers new metro lines, more connectivity

HCMC considers new metro lines, more connectivity

Traffic news - 24/07/2023

The plan, announced by the HCMC Department of Transport, aims to synchronize the city’s urban railway network as part of the metropolis’ u...

NA members call for changing law to add birthplace to passports

NA members call for changing law to add birthplace to passports

Traffic news - 27/10/2022

The law does not require place of birth and this affects foreign relations and tourism, they said. Several countries like Germany, Spain, the Czech R...

Vietnam's biggest airport in the making still stuck at site clearance

Vietnam's biggest airport in the making still stuck at site clearance

Traffic news - 17/10/2022

Of the 2,532 ha of land earmarked for the first phase of the Long Thanh International Airport in Dong Nai Province that borders HCMC, the contractors...

Hanoi considers 6th metro line linking airport to new urban area

Hanoi considers 6th metro line linking airport to new urban area

Traffic news - 14/10/2022

The Hanoi People’s Committee has requested relevant units to study the new line (Noi Bai-Ngoc Hoi) using non-refundable ODA from the Australian...

Vaccination Schedule Vietnam Ministry of Health